CASE STUDIES

Scaling Manufacturing

Situation

OEM Customer needed to scale their first 2 Alpha Systems. Their End User needed 10 systems delivery within 8 month.

Problem

Incomplete system assembly and test documentation. Limited floor space/limited technicians, supply chain and infrastructure available for quick production scaling.

ODI Role

Owens Design and customer executed 3 phase plan:

  • Phase 1 – ODI Technical Experts at customer location - help build first tool with customer/redline docs/move BOM in MRP
  • Phase 2 – Second, Third System assemblies executed at ODI with customer expert on site at ODI, consigned materials
  • Phase 3 – Reminder of systems assembled and tested at ODI including material purchasing – Full Turnk